May 25, 2009 - Pre-construction    
Still kind of freaky to see this sign and know
that they mean "me".    In fact, I'm still kind
of detached from it and it hasn't sunken in
that this will be my piece of dirt.
My lot flagged out and marked for the
driveway cut-out.
There's a pretty big drainage easement
behind me, so there will be a good gap
between me and the neighbors to the rear.

 

June 14, 2009 - Construction started on June 12th
Forms & fill dirt is in.   Funny how small it seems when it's
at this point in the process.

 

June 21, 2009    
 
Forgot my camera, so mediocre cellphone pic's will have
to do this week..   The foundation is all trenched out, some
of the plumbing is done, but I don't see any electrical yet.  
Pic 4 & 5 show the lovely weeds for my backyard!!
   

 

June 28, 2009    
Not a lot of exciting work done this week, pretty much
finishing the framing for the foundation and putting in the
tension cables.   Supposedly they are going to pour the
foundation no later than Wednesday, and start framing
the next Wednesday.   It supposed to rain Tuesday, that
might delay things a little bit.
   

 

July 2, 2009    
 
Pardon my finger in the shots, it was an unplanned trip
and I didn't have my camera, so crappy cell phone pic's
again.   Pic 2 is my garage, 3 & 4 are the front door,
and pic 5 is the kitchen.   Lumber delivery is scheduled
for Tuesday and start framing on Wednesday, so things
are about to really start cranking.
   

 

July 8, 2009    
Amazing how fast it starts to look like a house when
everything is pre-built and assembled like a puzzle!!
There is still a little bit more framing to do, but not
very much.
 

 

July 18, 2009    
Lots of work done last week!!   The pile of bricks
is probably good thing.   Most of the plumbing is
done, bathtub & shower are there but not installed
yet.
 

 

August 2, 2009 - No new pic's last week, they didn't do anything picture worthy really.    
Stoked that I finally get to park in my driveway!!
Bricks were done this week, as well as more interior
wiring for the alarm.   The inside is still just 2x4's, nothing
to note there.    Framing inspection was done last week,
and we have a pre-drywall walk thru & inspection on
Wednesday.
Sorry, if I have to see the Honey Pot then so do you!!

 

August 9, 2009
I ended up making an unplanned trip out these yesterday, no camera or cell phone with me so no pictures this week.

Dry-wall was put up, so it looks like a house on the inside now too.   No problems with the inspection last Wednesday

 

August 16, 2009    
Entering through the front door into the living room Living room from the extra bedroom & garage hall Kitchen from the back door
Laundry, 'frig nook, and MBR hall Living room thru the kitchen counter opening Master bath
Front bedroom & hall closet Garage More garage
Even more garage
Someone else said the house "is as it should be,
mostly garage!"
Other extra BR, it will be my office Living room towards extra BR/garage hall,
Entertainment nook to the left

 

August 29, 2009    
   

 

September 7, 2009

Since they have added things that could get stolen they have started locking the place up, so I couldn't get in to take pic's but I got this one of the kitchen floor last week.   This is temporary flooring, I plan to install slate (or something) within 2 years.

Sinks, faucets, and commodes have been installed.

 

September 11, 2009    
 
Looks like we're getting ready for sod.
  

Just a basic & cheap sink, I'll get something cool when I do granite.
 
   

 

September 18, 2009    

My Realtor, Orlando Perez, wallering on my new
carpet.... some people, geez...
 

 

September 25, 2009

Getting pretty close to being done, just some semi-minor
"fix-it" work to do.   I took some paint samples out today
to see what I like, so I'll be ready to roll on that right
away... which should be somewhere around Oct. 10th.